Cargo lift installation procedures, safe operating precautions

A preparation based on:

Instructions made according to cargo lifts, construction organization design and on-site geological conditions.

Second, the construction side of the preparatory work before the job:

(1) Check the job site with or without pits, trenches, culverts, dark hole, top with or without power lines, communication lines. If you have the above phenomenon, take support measures.
(2) Check whether the obstacle out of the way.
(3) tools to participate in the lift installation and removal operations use various types of work, toolbox, rigging, tie clip, helmets, safety belts and other items, the arrival of the job-site backup.

Third, the foundation:

Lift foundation has been dealt with by the civil construction is completed units.

Fourth, the safe operation of the basic requirements:

Staff (1) Participation must be familiar with the installation and dismantling of lifts and mechanical properties, structural features and have skilled technique and ability to exclude general failure.
(2) Workers involved in this work should be a clear division of duties, specifically one person is responsible for directing the work, to determine command liaison signals.
(3) comply with all formulated to ensure the safe production discipline, safety equipment to carry complete health personnel in high-altitude operations must comply with the relevant provisions of the labor department, Do not drink and jobs.
(4) In case of snow, rain, fog and wind speed over 13 m / sec weather can not perform this operation.
(5) the construction site transformer power supply grid, the transformer capacity of not less than 100KVA.

Fifth, after the installation of the examination:

(1) Re-check the fastening point meets the requirements, if loose should be tightened.
(2) Check all parts are complete and active.
Sixth, the installation:
(1) crane commissioning including commissioning, static load test and dynamic load operation. Before the end of the previous step may not be qualified commissioning the next step.
(2) clean up the construction site of industrial equipment, rigging, equipment and debris.
(3) The exit of personnel and equipment.